Wednesday, December 29, 2010

2010-12-29 Unit GW


Master Bedroom can be seen from 2nd Bedroom. Workers are removing marble floor in Master Bath.

2010-12-29 Unit GE


All drywall has been removed from Master Bedroom.


All drywall has been removed from Master Bedroom.


All drywall has been removed from Master Bedroom and Master Bath.


All drywall has been removed from Master Bedroom. Existing insulation can be seen along east wall of Master Bedroom. Lavatory is temporarily stored in Master Bedroom.


Guest lavatory is temporarily installed in 2nd Bedroom. Existing leveling boards can be seen here in 2nd bedroom. A good portion of existing drywall has been removed from this room.


All drywall and finishes have been removed from Master Bath.

Friday, December 17, 2010

2010-12-17 Units 3W & 3E


Unit 3E – Mechanical closet can be seen in background beyond 2nd bedroom closet. Plywood subfloor has been installed in bedroom and corridor.


Unit 3E – Mechanical closet can be seen in background beyond 2nd bedroom closet. Supply duct can be seen in ceiling as it exits mechanical closet.


Unit 3W – All dry wall has been removed from Master Bathroom.


Unit 3W – All dry wall has been removed from Master Bathroom. All finished marble has been removed from Master Bathroom.

Thursday, December 16, 2010

2010-12-16 Unit 3E


Newly installed joists in Living Room with moisture barrier applied along demising wall between Unit 3E & 3W.


Kitchen protected with plywood, cardboard and plastic.


Gypsum board has been fully removed from Master bedroom. Plywood subfloor has been installed in Master bedroom.


Gypsum board has been fully removed from Master bedroom. Plywood subfloor has been installed in Master bedroom and Master bath.


Gypsum board has been fully removed from Master bedroom. Plywood subfloor has been installed in Master bedroom and Master bath.


Gypsum board removed from demising wall in corridor from rear deck. Plywood subfloor has been installed in corridor.

Wednesday, November 10, 2010

2010-11-10


Roofers remove blue tarp from north portion of roof to complete roof membrane installation.


Plywood deck has be cleaned of debris as roofers prepare to complete roof installation.


Plywood deck has be cleaned of debris as roofers prepare to complete roof installation.


Skylight has been reset atop waterproof curb.


South end of roof looking over unit 3E bay window and east parapet wall in background.

Tuesday, November 9, 2010

2010-11-09


East parapet wall with waterproof roof membrane and counter flashing.


Roofer heat welding roof membrane around vent.


Roofer heat welding roof membrane around vent.


Roofer installing waterproof roof membrane up west parapet wall.


Roofer heat welding roof membrane to west parapet.


Roofer heat welding roof membrane to west parapet.


Roofer positioning roof membrane around stairway skylight.


Roofer heat welding roof membrane to corner of skylight.


This picture shows three layers that make up the new roof.


CertainTeed Base Sheets.


APP 160 Roof membrane with vent cap.


Aluminum Roof coating.


Cant strip at base of parapet wall.


North parapet wall has been partially built for immediate installation of roof membrane. This picture shows counter flashing in wall with weep cords.


Top of north parapet wall just above curved bay window.

Wednesday, November 3, 2010

2010-11-03


New east brick parapet wall with new clay cap.


Corner flashing detail.


New west brick parapet wall with new clay cap.


View of roof from the southwest looking northeast. Roof deck is completed and covered with tarp.


South end of east parapet wall.


New west wall parapet with counter flashing. Blue tarp is protecting completed plywood deck.