Monday, January 3, 2011

2011-01-03 GE


South wall of Master Bedroom


View looking at Master Bedroom and Master Bath.


Guest Bathroom can be seen in background from 2nd Bedroom.


New header for closet has been installed. New joists are anchored to header and support floor above.


Three to four feet of drywall has been removed from south wall of Guest Bath. 2nd Bedroom can be seen beyond plumbing chase.

Thursday, December 30, 2010

2010-12-30 Roof Intake & Exhaust


Mechanical Contractor has been busy installing intake and exhaust for individual unit furnaces. Sheet metal curbs to be finished with roofing material by roofer.


Mechanical Contractor has been busy installing intake and exhaust for individual unit furnaces. Sheet metal curbs to be finished with roofing material by roofer.


Mechanical Contractor has been busy installing intake and exhaust for individual unit furnaces. Sheet metal curbs to be finished with roofing material by roofer.

2010-12-30 Unit GW


New plywood leans against demising wall in corridor for new plywood sub-floor.


New plywood sub-floor has been installed in 2nd Bedroom. Plumbing pipes and bath tub to 2nd Bathroom can be seen in background.


New plywood sub-floor installed over existing wood leveling boards or sleepers. Sleepers are anchored to concrete slab.


New head and jambs were installed for 2nd Bedroom closet today.


All drywall and finishes have been removed from Master Bath.


Steel column and steel beam can be seen here in Master Bath running from back of building, through Master Bathroom and all the way north to Living Room. This steel beam only occurs in basement units supporting first floor above.

Wednesday, December 29, 2010

2010-12-29 Unit 3E


All drywall has been removed from Master Bedroom.


All finishes have been removed from Master Bath. Whirlpool tub remains in tack.


All finishes have been removed from Master Bath. Plywood sub-floor has been installed in Master Bath.


Laundry closet and Mechanical closet can been seen in background behind Master Bath.

2010-12-29 Unit 2E


Master Bedroom can be seen in background from 2nd Bedroom. Most of the drywall has been removed from the 2nd Bedroom.


Master Bedroom can be seen in background from 2nd Bdroom. Most of the drywall has been removed from the 2nd Bedroom.


Supports have been installed for existing failing beams between Living Room and Kitchen.


Furnace has been reinstalled. Master Bath can be seen in background. All drywall and marble has been removed.


All drywall has been removed from Master Bedroom and Bath.


All drywall has been removed from Master Bedroom. Master Bath lavatory, sinks, counter top and cabinet are stored in Master Bathroom for the time being.

2010-12-29 Unit 1E


Washer and dryer can be seen in background of corridor. All drywall has been removed from corridor. Existing plumbing waste pipe can be seen at the very edge of existing wood stud.


Drywall has been removed from all walls in Master bedroom and Master bath with the exception of drywall around closets.


Drywall has been removed from all walls in Master bedroom and Master bath with the exception of drywall around closets.

2010-12-29 Unit GW


Master Bedroom can be seen from 2nd Bedroom. Workers are removing marble floor in Master Bath.