2010-10-22
Unit 3E Living Room is exposed to the sky as carpenters install new joists and decking.
Unit 3E Living Room is exposed to the sky as carpenters install new joists and decking.
NW corner of roof parapet where masonry meets stone.
East parapet where new masonry parapet meets adjoining building. Our next door neighbors have a raceway in the way of our new parapet.
2010-10-21
Masons finishing repair to south wall just above Unit 3W bay window.
Masons finishing repair to south wall just above Unit 3E bay window.
2010-10-20
West parapet wall under construction.
East parapet wall under construction.
North end of east parapet wall as wall meets building next door.
View looking north. North parapet wall has not been installed yet.
2010-10-07
Unit 3E Master bedroom is open to the sky above as workers install new joists and wood decking.
Unit 3E Guest bathroom is open to sky above as workers install new joists and wood decking.
Unit 3E Guest bedroom ceiling is open to existing joists.
Unit 3E from above roof looking down at existing joists.
2010-10-06
View from unit 3W looking into Dining/Kitchen area with demising wall in background. Top of demising wall has to be modified to accept new joists.
View of existing framing from roof, above unit 3E.
View of existing joists from roof, above unit 3E Masterbedroom.
Newly installed joists sit on top of demising wall between unit 3E & 3W. Ends of joists are wrapped with moisture barrier. New plywood decking fastened to joists.
View of roof looking south. West portion of roof has new joists, and new decking covered with blue tarp. East portion of roof is being worked on.
Saturday, October 23, 2010
2004-10-04
Carpenters installing joists above 3W.
Newly installed joists above unit 3W.
Newly installed joists above unit 3W kitchen.
New LVL joists installed at demising wall between unit 3W and 3E.
Temporary shoring in Unit 3E has been installed at demising wall until new joists can be set in place.
Temporary shoring in Unit 3E has been installed at demising wall until new joists can be set in place.
Ends of joists are wrapped with moisture barrier. LT19 masonry anchor on top of joists.
Sunday, October 3, 2010
2010-10-03
New wood joists and plywood decking have been installed on west half of building. Moisture barriers have been installed on ends of new joists.
The living room of unit 3W is open to the sky as JBD prepares to remove the last few remaining wood joist and replace with new.
Worker installs new joists on east side of Unit 3W – living room.
View from roof looking north, edge of roof along west side of building is exposed as new wood joist have been installed with moisture barriers on ends.
Workers installing new wood joist above Unit 3W.
Workers installing new wood joist above Unit 3W.
Friday, October 1, 2010
2010-10-01
Old roofing and plywood decking has been removed from west half of building.
Old roofing and plywood decking has been removed from west half of building.
West edge of roof is exposed. Ends of existing wood joists are exposed.
Shown to the left is the top of the existing gutter and on the right is the existing water heater exhaust.