Tuesday, September 27, 2011

ECCA - 09-27-2011 Deck Work Completed

Back deck is completely primed and painted.

Back deck is completely primed and painted.

New deck has been fully installed on third floor. Damaged deck boards throughout the decks have been replaced.

New deck has been fully installed on third floor. Damaged deck boards throughout the decks have been replaced.

ECCA - 08-25-2011 Deck Work

August 21, through August 31, 2011, Deck Construction workers primed and painted exposed steel railings, columns and beams.

Workers have primed gates and railings to receive paint.

Third floor has been primed and painted as workers continue painting from the top floors down to the ground.

Workers have been working on replacing old wood decking with new deck boards.

Workers have been working on replacing old wood decking with new deck boards.

Tuesday, March 8, 2011

2011-03-08 3E


Dry wall is being installed in Master Bedroom.


Dry wall is being installed in Master Bedroom.


Dry wall is being installed in Master Bedroom.


Dry wall is being installed in Master Bath.


Drywall is being installed in corridor around Washer/Dryer closet.


Dry wall is being installed in 2nd Bedroom.


Flooring is being installed in Dining Room & Kitchen.

2011-03-08 2E


Master Bedroom is being drywalled - south wall.


Master Bedroom is being drywalled - east wall.


Master Bedroom is being drywalled - north wall towards closets.


2nd Bedroom is being drywalled.

2011-03-08 GW


Master bedroom has been fully drywalled and primed for paint. Baseboard and crown moldings have been installed.


Closets in Master bedroom have been fully drywalled and primed for paint. Baseboard has been installed.


Master Bathroom has been taped, sanded, primed and ready for paint.


Master Bathroom has been taped, sanded, primed and ready for paint.


Master Bathroom has been taped, sanded, primed and ready for paint. New Door has been installed.


2nd Bedroom has been taped, sanded, primed and ready for paint. Crown molding is in place. New Bi-fold doors have been painted and installed.


Baseboard is being installed.


2nd Bedroom has been taped, sanded, primed and ready for paint. Crown molding is in place.

2011-03-08 GE


Drywall in Master Bedroom has been taped. Baseboard and ceiling molding have been installed.


Cement board and drywall in Master Bath have been taped.


Drywall in master Bedroom closets has been taped.


Drywall in 2nd Bedroom has been taped. Baseboard and ceiling molding have been installed.


Drywall in Guest Bathroom has been taped.


Drywall in Guest Bathroom has been taped.


Drywall has been taped throughout Corridor. Baseboard and crown moldings have been installed.

2011-03-08 1E


1st coat of paint has been applied to 3rd bedroom. Wood floors have been installed.

Monday, March 7, 2011

2011-03-07 3W


Dining Room and Kitchen are being drywalled.


Kitchen is being drywalled.


Living Room is being drywalled.


Living Room is being drywalled.


3rd Bedroom has been drywalled.


Drywall is being installed in rear corridor.

2011-03-07 3E


Dining Room and Kitchen are being drywalled.


Dining Room and Kitchen are being drywalled.


Living Room is being drywalled.


Living Room is being drywalled.

2011-03-07 1E


Floors are being installed in back half of unit.


Floors are being installed in back half of unit in corridor.

2011-03-07 1W


Worker taping drywall inside Master Bedroom closets.


Master Bath has been drywalled and taped.


Master Bath has been drywalled and taped. Plywood subfloor is in place.


Doors and various construction supplies are temporarily stored in Living Room.


Doors and various construction supplies are temporarily stored in Living Room. Kitchen cabinets are covered with plastic. Counter tops are covered with Styrofoam boards.