Tuesday, March 8, 2011

2011-03-08 GW


Master bedroom has been fully drywalled and primed for paint. Baseboard and crown moldings have been installed.


Closets in Master bedroom have been fully drywalled and primed for paint. Baseboard has been installed.


Master Bathroom has been taped, sanded, primed and ready for paint.


Master Bathroom has been taped, sanded, primed and ready for paint.


Master Bathroom has been taped, sanded, primed and ready for paint. New Door has been installed.


2nd Bedroom has been taped, sanded, primed and ready for paint. Crown molding is in place. New Bi-fold doors have been painted and installed.


Baseboard is being installed.


2nd Bedroom has been taped, sanded, primed and ready for paint. Crown molding is in place.