2011-03-01 2E


New doors are drying after being painted.


Kitchen area protected with cardboard and plastic.


Doors and trim have been removed in corridor.


2nd Bedroom is being painted.


Corner of Master Bedroom awaits drywall.


Wood flooring has been delivered and acclimates to on-site conditions before being installed throughout the building.


Master Bath cement board has been taped and is ready for paint.