There is a large gap below existing aluminum threshold. This space should be filled with insulation, backer rod and sealant. There is a large gap between the aluminum threshold and bottom of door. This gap should be sealed with weatherstripping.
Tuesday, January 18, 2011
2011-01-18_2E
There is a large gap below existing aluminum threshold. This space should be filled with insulation, backer rod and sealant. There is a large gap between the aluminum threshold and bottom of door. This gap should be sealed with weatherstripping.
2011-01-18_2W
Portion of rear wall in laundry closet has been removed to access pipes for building furnaces.
2011-01-18 GE
Drywall was removed from brick demising wall uncovering a doorway full of thermal insulation. This doorway will get filled with Concrete Masonry Units.
Drywall has been removed from back of washer/dryer closet exposing pipes for venting washer/dryers and furnaces above.
Drywall has been removed from back of washer/dryer closet exposing pipes for venting washer/dryers and furnaces above.
Mold resistant latex paint has been applied to open walls once covered with moldy drywall.
Mold resistant latex paint has been applied to open walls once covered with moldy drywall.
2011-01-18 1W
Door seal is missing from bottom of door and there is a large gap between door and threshold.
Mason has placed sand buckets in preparation of interior masonry work.
Friday, January 7, 2011
2011-01-11 3W
Carpenters started installing metal furring for gyp bd soffits in Kitchen & Dining Area.
Cut metal studs for gyp bd soffit are being stored on top of newly installed plywood sub-floor.
2011-01-07 2E
Closet in 2nd Bedroom has been framed. New joists have been set above header. New plywood sub-floor has been installed.
New sub-floor has been installed in 2nd Bedroom, Closet and Main Corridor.
Existing plumbing pipes to Guest Bathroom are exposed to 2nd Bedroom.
Existing plumbing pipes to Guest Bathroom are exposed to 2nd Bedroom.
Existing plumbing pipes to Guest Bathroom are exposed to 2nd Bedroom.
East wall and ceiling are exposed.
Ceiling is exposed. Existing supply duct and vent are shown on the leftt. Three (3) new joists are shown in the center. Existing washer/Dryer exhaust duct is shown on the right venting to outside of building.
East wall with existing wood furring strips.
2011-01-07 2W
Wood sub-floor has been installed in 2nd Bedroom. Carpenters framed closet in 2nd Bedroom.
Now that new joists have been installed in ceiling, carpenters will be able to install sub-floor in unit 3W next week.