Thursday, December 30, 2010
2010-12-30 Roof Intake & Exhaust
Mechanical Contractor has been busy installing intake and exhaust for individual unit furnaces. Sheet metal curbs to be finished with roofing material by roofer.
Mechanical Contractor has been busy installing intake and exhaust for individual unit furnaces. Sheet metal curbs to be finished with roofing material by roofer.
Mechanical Contractor has been busy installing intake and exhaust for individual unit furnaces. Sheet metal curbs to be finished with roofing material by roofer.
2010-12-30 Unit GW
New plywood leans against demising wall in corridor for new plywood sub-floor.
New plywood sub-floor has been installed in 2nd Bedroom. Plumbing pipes and bath tub to 2nd Bathroom can be seen in background.
New plywood sub-floor installed over existing wood leveling boards or sleepers. Sleepers are anchored to concrete slab.
New head and jambs were installed for 2nd Bedroom closet today.
All drywall and finishes have been removed from Master Bath.
Steel column and steel beam can be seen here in Master Bath running from back of building, through Master Bathroom and all the way north to Living Room. This steel beam only occurs in basement units supporting first floor above.
Wednesday, December 29, 2010
2010-12-29 Unit 3E
All drywall has been removed from Master Bedroom.
All finishes have been removed from Master Bath. Whirlpool tub remains in tack.
All finishes have been removed from Master Bath. Plywood sub-floor has been installed in Master Bath.
Laundry closet and Mechanical closet can been seen in background behind Master Bath.
2010-12-29 Unit 2E
Master Bedroom can be seen in background from 2nd Bedroom. Most of the drywall has been removed from the 2nd Bedroom.
Master Bedroom can be seen in background from 2nd Bdroom. Most of the drywall has been removed from the 2nd Bedroom.
Supports have been installed for existing failing beams between Living Room and Kitchen.
Furnace has been reinstalled. Master Bath can be seen in background. All drywall and marble has been removed.
All drywall has been removed from Master Bedroom and Bath.
All drywall has been removed from Master Bedroom. Master Bath lavatory, sinks, counter top and cabinet are stored in Master Bathroom for the time being.
2010-12-29 Unit 1E
Washer and dryer can be seen in background of corridor. All drywall has been removed from corridor. Existing plumbing waste pipe can be seen at the very edge of existing wood stud.
Drywall has been removed from all walls in Master bedroom and Master bath with the exception of drywall around closets.
Drywall has been removed from all walls in Master bedroom and Master bath with the exception of drywall around closets.
2010-12-29 Unit GW
Master Bedroom can be seen from 2nd Bedroom. Workers are removing marble floor in Master Bath.
2010-12-29 Unit GE
All drywall has been removed from Master Bedroom.
All drywall has been removed from Master Bedroom.
All drywall has been removed from Master Bedroom and Master Bath.
All drywall has been removed from Master Bedroom. Existing insulation can be seen along east wall of Master Bedroom. Lavatory is temporarily stored in Master Bedroom.
Guest lavatory is temporarily installed in 2nd Bedroom. Existing leveling boards can be seen here in 2nd bedroom. A good portion of existing drywall has been removed from this room.
All drywall and finishes have been removed from Master Bath.
Friday, December 17, 2010
2010-12-17 Units 3W & 3E
Unit 3E – Mechanical closet can be seen in background beyond 2nd bedroom closet. Plywood subfloor has been installed in bedroom and corridor.
Unit 3E – Mechanical closet can be seen in background beyond 2nd bedroom closet. Supply duct can be seen in ceiling as it exits mechanical closet.
Unit 3W – All dry wall has been removed from Master Bathroom.
Unit 3W – All dry wall has been removed from Master Bathroom. All finished marble has been removed from Master Bathroom.
Thursday, December 16, 2010
2010-12-16 Unit 3E
Newly installed joists in Living Room with moisture barrier applied along demising wall between Unit 3E & 3W.
Kitchen protected with plywood, cardboard and plastic.
Gypsum board has been fully removed from Master bedroom. Plywood subfloor has been installed in Master bedroom.
Gypsum board has been fully removed from Master bedroom. Plywood subfloor has been installed in Master bedroom and Master bath.
Gypsum board has been fully removed from Master bedroom. Plywood subfloor has been installed in Master bedroom and Master bath.
Gypsum board removed from demising wall in corridor from rear deck. Plywood subfloor has been installed in corridor.
Wednesday, November 10, 2010
2010-11-10
Roofers remove blue tarp from north portion of roof to complete roof membrane installation.
Plywood deck has be cleaned of debris as roofers prepare to complete roof installation.
Plywood deck has be cleaned of debris as roofers prepare to complete roof installation.
Skylight has been reset atop waterproof curb.
South end of roof looking over unit 3E bay window and east parapet wall in background.
Tuesday, November 9, 2010
2010-11-09
East parapet wall with waterproof roof membrane and counter flashing.
Roofer heat welding roof membrane around vent.
Roofer heat welding roof membrane around vent.
Roofer installing waterproof roof membrane up west parapet wall.
Roofer heat welding roof membrane to west parapet.
Roofer heat welding roof membrane to west parapet.
Roofer positioning roof membrane around stairway skylight.
Roofer heat welding roof membrane to corner of skylight.
This picture shows three layers that make up the new roof.
CertainTeed Base Sheets.
APP 160 Roof membrane with vent cap.
Aluminum Roof coating.
Cant strip at base of parapet wall.
North parapet wall has been partially built for immediate installation of roof membrane. This picture shows counter flashing in wall with weep cords.
Top of north parapet wall just above curved bay window.
Subscribe to: