New plywood leans against demising wall in corridor for new plywood sub-floor.


New plywood sub-floor has been installed in 2nd Bedroom. Plumbing pipes and bath tub to 2nd Bathroom can be seen in background.


New plywood sub-floor installed over existing wood leveling boards or sleepers. Sleepers are anchored to concrete slab.


New head and jambs were installed for 2nd Bedroom closet today.


All drywall and finishes have been removed from Master Bath.


Steel column and steel beam can be seen here in Master Bath running from back of building, through Master Bathroom and all the way north to Living Room. This steel beam only occurs in basement units supporting first floor above.